Quick update 2-5-2017

Everyone at the factory is returning for work this week.  We passed $190,000 in orders recently!

The immediate priorities are to get in hand the remaining first-run parts made to my specifications:  buckling springs, top/bottom inner assembly, boxes, and the keys.  After these parts have been approved, production will continue from where it left off (production has finished on the flippers, barrels, original style cases, capacitive PCB, controller PCB, ribbon cable to attach the two PCBs, and USB cables).

At this point we are waiting on the factory to do everything to spec.  I will not approve or send out something that I would not want to use myself, something not to my specifications and level of quality.